How much diesel your standby generators need on site for a runtime target at N load, and the tanks that hold it.

Your generators

Count the generators running to carry the site load. Redundant units on standby (the +1 of N+1) don't burn fuel at N load.
From the generator datasheet's fuel consumption table, at the load each set will run at.
The Uptime Institute minimum is 12 hours at N load for every Tier. Many owners store more.
Fuel below the outlet that can't be drawn, plus the space left empty at the top. Leave blank to see usable fuel only.
Where the tanks go

The figures above are an example to start from. Replace them with your own.

Result

Send these figures to a sales engineer covering your state. We reply within 2 business days.

Send these specs for a quote

How the calculator works

  • Fuel use at N load is the number of generators carrying the load multiplied by each generator's fuel use at that load.
  • Usable fuel is that hourly use multiplied by your runtime target.
  • Storage to provide adds your allowance for fuel that can't be drawn and the empty space at the top of the tank.
  • Tank options divide the storage across the fewest tanks of each type, using the largest size we publish: up to 110,000L of diesel in a self-bunded tank, 150,000L in a single-wall horizontal or double-wall fibreglass tank, and 200,000L in a Glasteel® II tank. Fireguard® tanks are sized to suit.

The Uptime Institute Tier Standard: Topology sets a minimum of 12 hours of on-site fuel at N load for every Tier. Read more on our data centre diesel storage page.

This calculator is general information to help with early sizing. Your engineer and the site's approvals set the final design.